Day 49: Masonry Work - Day 7 (Retaining Wall & Coping)
Day 49: Masonry Work - Day 7 (Retaining Wall & Coping)
The rain is gone and Bob is back with his crew. WOO HOO! Have I mentioned how talented these guys are and how they don't stop? Since the rain has passed us they are working on capping off the retaining wall and installing those lights. They also finished up the majority of the coping around the pool.
You can see the low voltage light sitting under the cap of the retaining wall.
In this shot you can see a close up of the light that will be shining down the retaining wall. This was a great idea provided by Sal at Sal's Landscaping.
There is about seven more feet to cap off on top of the retaining wall and we are done!